FERC Approves PJM Large Load Registry but Rejects Curtailment Proposal

Illustration of a grid analyst reviewing a large load registry for data center planning

FERC approved PJM’s large-load registry but rejected its proposed Interim Resource Adequacy Service (IRAS) tariff on October 9, 2026. The decision in Docket ER26-3515-000 allows PJM to improve visibility into very large new electricity customers, including data centers, while declining the proposed approach that would expose certain new loads to mandatory curtailment.

The distinction matters: a registry is a planning and information tool; IRAS was a proposed service and emergency curtailment framework. FERC did not announce a universal ban on disconnecting data centers in electrical emergencies, nor did it approve the entire PJM package.

What FERC Decided on October 9, 2026

PJM proposalOctober 9 resultPractical implication
Definition and registry for Large LoadsAccepted in partMore structured information for grid planning
Interim Resource Adequacy Service (IRAS)RejectedProposed special service and associated curtailment mechanism not approved
Bring Your Own New Capacity rulesRejected as linked to IRASAssociated capacity framework needs more work
Exclusion of some new load from capacity demand curveRejected as linked to IRASCapacity-market treatment was not adopted as filed

FERC’s official order is identified as 197 FERC ¶ 61,019, accession number 20261009-3055. That is the primary record to consult instead of treating social-media summaries or investor headlines as the decision itself.

What Counts as a Large Load Under the Registry?

The approved definition captures an end-use customer with a cumulative peak load of 50 MW or more at a single electrical site. Affiliated facilities within the specified one-mile grouping rule can be considered together. The threshold is about substantial customer demand, not exclusively AI or data-center use.

A 50 MW data center operating continuously at full load for one day would consume 50 MW × 24 hours = 1,200 MWh. At a 90% load factor, the daily energy would be 1,080 MWh. This is an illustrative conversion, not an estimate of the facilities listed in the registry.

PJM needs reliable forecasts of service dates, expected load, location, and whether associated new resources are planned. These details can improve studies, but collecting better data does not itself build a transformer, transmission line, or power plant.

As an eBay Partner, I may be compensated if you make a purchase.

What IRAS Would Have Changed

PJM’s August 2026 filing proposed Interim Resource Adequacy Service as a way to connect new large customers while trying to avoid shortages or higher costs for existing customers. The design distinguished large loads that brought new supply from those that did not. Some proposed service arrangements could have required involuntary reductions during system stress.

The controversial provision involved the order in which new IRAS customers could be curtailed relative to other load and existing demand-response resources. The proposal was more than a data-collection rule: it directly affected service, reliability obligations, and the signals the capacity market would send to resource developers.

Why FERC Rejected the Curtailment Framework

The decision raised concerns about whether parts of the proposal reached into matters traditionally governed by states, including retail service arrangements, and whether the different treatment of particular large loads was adequately justified as non-discriminatory.

A separate concurring statement emphasized that PJM would need to justify requiring IRAS customers to curtail before customers who had voluntarily enrolled in demand response. The commissioner also warned that excluding those loads from the capacity-market demand curve could create misleading price signals about the resources the region actually needs.

That separate statement explains an important concern, but it is not interchangeable with every binding finding in the Commission’s order. Readers should distinguish the Commission’s official ruling from a commissioner’s additional reasoning.

Did FERC Ban Data Center Power Curtailment?

No. FERC rejected a specific set of tariff revisions submitted by PJM in this docket. The decision should not be described as a blanket prohibition on utilities, grid operators, or state regulators using lawful emergency measures affecting data centers.

Emergency procedures, state retail-service rules, contracts, voluntary demand-response programs, and future approved PJM tariffs remain relevant. A revised proposal may be filed, but it would require its own regulatory review and supporting justification.

Why Registry Data Matters to Grid Reliability

Large loads do not necessarily arrive evenly across a region. Many data centers cluster where fiber access, land, tax incentives, and utility infrastructure are attractive. One county can see a major jump in projected demand even if the region-wide average appears manageable.

Better registration can reduce uncertainty in the planning process: PJM can distinguish realistic service dates from speculative proposals, compare expected demand with resource additions, and identify when high-voltage infrastructure must be upgraded.

For background, see PJM Data Center Reliability Risks From 2027 and AI Data Center Power Consumption in the United States.

What This Means for Ordinary Electricity Customers

The consumer-cost question is separate from the registry’s administration. If load growth requires new substations, transmission, capacity resources, or upgrades, regulators must decide which parties pay. A new data center may create valuable economic activity, but those benefits do not automatically answer how infrastructure costs should be allocated.

On the other hand, constraining every new large load without clear rules could create uncertainty for generation investment and contracted grid upgrades. Policy must balance reliable service, cost causation, timely development, and non-discriminatory tariffs.

Related analysis: Why PJM Electricity Prices Are Rising Faster Than the U.S. Average.

Markets: What Investors Should and Should Not Infer

The ruling does not establish that data-center power demand will be served without restriction, that new capacity will arrive on schedule, or that every power generator automatically benefits. It means one proposed mechanism failed while a narrower information-gathering measure advanced.

For utility and power-market analysis, watch grid construction schedules, capacity-market reforms, new generation commitments, and whether the load forecast becomes more reliable. The effect on retail bills depends on future tariff designs and cost-allocation decisions, not the headline alone.

A related cost-allocation case is discussed in Who Should Pay Data Center Transmission Costs?.

What Happens Next?

  • PJM must implement the accepted registry provisions and comply with the order’s requirements.
  • PJM may rework and refile rejected elements, subject to new justification and review.
  • Developers should watch how projected demand and new capacity are counted in PJM resource adequacy.
  • State regulators and utilities still influence retail service terms and emergency treatment.
  • Customers should distinguish approved tariff language from pending proposals and company announcements.

Bottom Line

The October 9 FERC decision is best described as registry accepted, proposed IRAS curtailment service rejected. The accepted registration system may improve visibility into 50 MW-plus demand. The rejected provisions did not establish the proposed mandatory interruption arrangement or the linked capacity-market changes.

This is a meaningful regulatory development, not the end of PJM’s large-load problem. Actual grid reliability will depend on new supply, workable service rules, realistic forecasts, and who funds the infrastructure needed to serve growing data-center demand.

About the author

I have practical experience in electrical construction and electrical project coordination in South Korea. For U.S.-focused guides, I research official codes, government data, utility documents, and manufacturer specifications to explain electrical and energy topics as accurately and practically as possible.

Sources & Official References

As an eBay Partner, I may be compensated if you make a purchase.

Is there something you’d like to see?

Suggest an electrical topic, practical guide, or calculator you would like to see on JHOTAS-LAB. Your suggestion may help shape future content.